kejora

LKJT/PBPP/SG.MUPOR/P/2024/SH2703

CADANGAN KERJA-KERJA MENAIKTARAF SISTEM PERPARITAN DI KAWASAN PERTANIAN SUNGAI MUPOR , MUKIM ULU SUNGAI SEDILI BESAR, DAERAH KOTA TINGGI, JOHOR DARUL TA'ZIM.

No. Petender Harga Tempoh (Minggu)
4/ 33 208,000.50 8
29/ 33 211,050.00 8
2/ 33 211,600.00 12
27/ 33 211,600.00 8
28/ 33 212,000.00 8
24/ 33 212,260.00 8
31/ 33 212,750.00 8
12/ 33 213,697.00 8
9/ 33 213,785.00 12
19/ 33 213,900.00 8
20/ 33 214,935.00 8
32/ 33 215,001.00 7
13/ 33 215,855.00 8
18/ 33 216,220.00 8
23/ 33 217,007.00 7
26/ 33 217,644.00 10
11/ 33 217,966.32 8
16/ 33 218,270.00 8
5/ 33 219,301.80 8
6/ 33 219,630.00 8
33/ 33 219,990.00 7
14/ 33 220,550.00 10
1/ 33 220,880.00 8
15/ 33 222,215.00 8
10/ 33 222,240.00 12
25/ 33 223,003.00 7
3/ 33 223,075.00 8
30/ 33 225,005.00 7
21/ 33 225,398.10 8
22/ 33 226,549.00 8
17/ 33 227,980.00 8
7/ 33 228,014.50 8
8/ 33 229,420.00 6
Showing entries (filtered from total entries)